Dive into the latest chapter of architectural excellence and progress with our December 2023 Construction Update for Sunshine Beach Resort & Residences by T.H. Group. This coastal haven, poised on Bangtao Beach, is witnessing remarkable strides in its development.
Building A4:
Installation of plumbing and electrical pipelines on the second to fourth floors is 100% complete.
Installation of windows on the second to fourth floors is 100% complete.
Plastering of internal and external walls is 100% complete.
Air conditioning installation is 100% complete.
Model rooms are 100% complete.
Glass curtain wall in the lobby on the first floor is 100% complete.
Stone cave modeling template is 100% complete.
Ceiling and GRG framework welding is complete.
Marble and stone for the cave have arrived.
Hanging wall toilet tanks are 100% complete.
Building A5:
Masonry on the first floor is 95% complete.
Masonry on the second to fourth floors is 100% complete.
Plastering of internal walls on the second to fourth floors is 100% complete.
Pre-embedded installation of plumbing and electrical pipelines on the second to fourth floors is 95% complete.
Hanging wall toilet tanks are 45% complete.
Building E:
The main structure of Building E is 100% complete.
Masonry: 100% complete for floors one to five.
Pre-embedded installation of plumbing and electrical pipelines: 98% complete for floors one to five.
Internal wall plastering: 65% complete for the first and second floors, and 100% complete for the first, and third to fifth floors.
Hanging wall toilet tanks are 90% complete.
Installation of the freight elevator is 100% complete.
Building D:
The main structure of Building D is 100% complete.
Masonry: 85% complete for the first floor, and 100% complete for the second to fifth floors.
Pre-embedded installation of plumbing and electrical pipelines: 98% complete for floors one to five.
Internal wall plastering: 90% complete for the third and fourth floors.
Hanging wall toilet tanks are 75% complete.
Installation of the freight elevator is 100% complete.
Building C:
The main structure of Building C is 100% complete.
Masonry: 100% complete for floors one to five.
Pre-embedded installation of plumbing and electrical pipelines: 95% complete for floors one to five.
Internal wall plastering: 96% complete for floors one to three and five. 15% complete for the fourth floor.
Hanging wall toilet tanks are 65% complete.
Installation of the freight elevator is 30% complete.
Building B:
The main structure of Building B is 100% complete.
Masonry: 100% complete for floors one to five.
Pre-embedded installation of plumbing and electrical pipelines: 95% complete for the first floor, 85% complete for the second floor, and 50% complete for the third floor.
Hanging wall toilet tanks are 80% complete.
Installation of the freight elevator is 70% complete.
Building A1:
The main structure of Building A1 is 100% complete.
Masonry is 100% complete.
Pre-embedded installation of plumbing and electrical pipelines: 100% complete for floors one to four.
Internal wall plastering: 100% complete for floors one to four.
Hanging wall toilet tanks are 100% complete.
Installation of the freight elevator is 65% complete.
Air conditioning installation is 30% complete.
Installation of balcony doors and windows is 35%.
Building A2:
The main structure of Building A2 is 100% complete.
Masonry is 100% complete.
Pre-embedded installation of plumbing and electrical pipelines: 100% complete for floors one to four.
Internal wall plastering: 100% complete for floors one to four.
Hanging wall toilet tanks are 100% complete.
Installation of the freight elevator is 25% complete.
Air conditioning installation is 10%.
Building A3:
The main structure of Building A3 is 100% complete.
Masonry is 100% complete.
Pre-embedded installation of plumbing and electrical pipelines: 100% complete for floors one to four.
Internal wall plastering: 100% complete for floors one to four.
Hanging wall toilet tanks are 75% complete.
Installation of the freight elevator is 10%.
Perimeter Wall:
The rainwater pipes and roads on the north side sections of Buildings A5, D, and E are 100% complete.
The perimeter wall on the east side of the river channel is 100% complete.
In the upcoming month, the focus will be on the following construction activities:
Continuing the ongoing progress of the construction projects mentioned earlier.
Installing aluminum alloy doors and windows for Buildings A1 and E.
Commencing the decoration of the lobby and interior ceilings for Building A4.
Undertaking interior decoration for the model rooms in Building A5.
Finalizing the masonry on the first floor of Building D.
Conducting plastering for the walls of Buildings A5, B, C, D, and E.
Constructing the foundation beams for the perimeter wall along the river channel.
Progressing with the sewage treatment facilities on the east side of Buildings E and C, the construction of the No. 3 water tank on the north side of Building A1, and the water tanks for Buildings C and A3.
Advancing the main structure construction for Building G. Initiating the construction of the 10th pool.