Nearly all essential components of each building were completed in Phuket’s new Beachfront project Sunshine Beach Resort & Residences by T.H Group Phuket Co, Ltd.
Recent events on the Sunshine Beach project’s construction side are clarified by our sales manager, Daria.
Building A4:
2nd-floor plumbing and electrical installation are completed by 100%.
3rd-floor plumbing and electrical installation are completed by 100%.
4th-floor plumbing and electrical installation are completed by 20%.
Building D:
The 3rd-floor slab was completed 100%.
The 4th-floor slab was completed 100%.
Building C:
The 2nd-floor slab was completed 100%.
Building B:
Foundation completed 30%.
Building A1:
The pile foundation was completed 100%.
Sales office demolition is completed 100%, and A2 pile foundation construction started.