Explore the latest developments at Sunshine Beach Resort & Residences, a beacon of sophistication in Phuket’s real estate landscape. Our November construction update unveils the meticulous progress across various buildings, marking significant milestones in the creation of a luxurious condotel and premium residences.
Hydropower Pipeline Installation (2-4 Floors): Completed at 100%.
Windows Installation (2nd to 4th Floors): Currently at 40% completion.
Interior and Exterior Wall Plastering: Successfully completed at 100%.
Air Conditioning Sample Installations: In progress.
Glass Curtain Wall (1st-floor Hall): Successfully completed at 100%.
Stone Cave Molding Template Encapsulation: Accomplished at 100%.
Ceiling GRG Skeleton Welding: Currently underway.
Second-floor Masonry: Reached 95% completion.
Masonry (3-4 Floors): Successfully completed at 100%.
Hydropower Pipeline Installation (2-4 Floors): Currently at 95% completion.
Main Structure: Successfully completed at 100%. Masonry (1-5 Floors):
Currently at 99% completion.
Embedded Hydropower Pipeline Installation (1-3 Floors):
Currently at 95% completion.
Hydropower Pipeline Installation (4th and 5th Floors):
Currently at 90% completion.
Interior Wall Plastering:
First and Second Floors: Currently at 90% completion.
Third Floors: Currently at 93% completion.
Four Floors: Currently at 30% completion.
Main Structure: Successfully completed at 100%.
Masonry (2nd Floor): Reached 98% completion.
Masonry (3-4 Floors): Successfully completed at 100%.
Masonry (5th Floors): Currently at 99% completion.
Embedded Hydropower Pipeline Installation (2-4 Floors):
Currently at 95% completion.
Interior Wall Plastering (2-4 Floors): Currently at 95% completion.
Interior Wall Plastering:
Four Floors of Slurry Rejection: Currently at 55% completion.
Third Floors: Currently at 80% completion.
Main Structure: Successfully completed at 100%.
Masonry (1-3 Floors): Currently at 99% completion.
Masonry (4-5 Floors): Currently at 95% completion.
Embedded Hydropower Pipeline Installation:
1st Floor: Currently at 95% completion.
2nd Floor: Currently at 90% completion.
3rd Floor: Currently at 75% completion.
Interior Wall Plastering: 1st Floor:
Currently at 95% completion.
2nd Floor: Currently at 75% completion.
Main Structure: Successfully completed at 100%.
Masonry: 1st Floor: Currently at 99% completion.
2nd and 3rd Floors: Currently at 97% completion.
4th and 5th Floors: Currently at 92% completion.
Embedded Hydropower Pipeline Installation:
1st Floor: Currently at 95% completion.
2nd Floor: Currently at 85% completion.
3rd Floor: Currently at 50% completion.
Main Structure: Successfully completed at 100%.
Masonry: Successfully completed at 100%.
Embedded Hydropower Pipeline Installation:
1st and 2nd Floors: Currently at 100% completion.
3rd Floor: Currently at 95% completion.
Interior Wall Plastering:
1st to 4th Floors: Currently at 100% completion.
1st Floor: Currently at 100% completion.
2nd Floor: Currently at 25% completion.
Main Structure: Successfully completed at 100%.
Masonry: Successfully completed at 100%.
Embedded Hydropower Pipeline Installation:
1st to 3rd Floors: Currently at 100% completion.
4th Floor: Currently at 80% completion.
Interior Wall Plastering:
1st to 4th Floors: Currently at 100% completion.
1st and 2nd Floors: Currently at 100% completion.
3rd Floor: Currently at 18% completion.
Main Structure: Successfully completed at 100%.
Masonry: Successfully completed at 100%.
Embedded Hydropower Pipeline Installation (1-4 Floors):
Currently at 100% completion.
Interior Wall Plastering:
1st to 4th Floors: Currently at 100% completion.
1st Floor: Currently at 100% completion.
2nd Floor: Currently at 30% completion.
Main Structure: Successfully completed at 100%.
Masonry: Successfully completed at 100%.
Embedded Hydropower Pipeline Installation (1-4 Floors):
Currently at 100% completion.
Interior Wall Plastering:
1st to 4th Floors: Currently at 100% completion.
1st Floor: Currently at 100% completion.
2nd Floor: Currently at 30% completion.