Construction Update: September 2023 – Sunshine Beach Phuket

Construction Update: September 2023

Welcome to Sunshine Beach Resort & Resident’s September construction update. Explore the progress of our ambitious projects, where each brick and beam reflects our commitment to excellence. Here’s a glimpse of construction tapestry.

Building A4:
  • Plumbing and electrical pipelines on floors two to four: Completed at a stellar 100%.
  • Interior and exterior wall plastering: Meticulously finished at 100%.
  • Air conditioning installation: Progressing at 50%.
  • Model rooms: Taking shape at an impressive 30%.
Building A5:
Construction Progress:
  • Second-floor masonry: Laying the foundation at 30%.
  • Third-floor masonry: Soaring high at 95%.
  • Fourth-floor masonry: Solidifying at 90%.
  • Plumbing and electrical pipeline installation (floors two to four): Surging ahead at 90%.
  • Main structure: A towering achievement at 100%.
  • Floors one to four masonry: complete at 98%.
  • Plumbing and electrical pipeline installation (first and second floors): Nearly complete at 95%.
Building D:
  • Main structure: A monumental success at 100%.
  • Second to fifth-floor masonry: Progressing seamlessly at 95%.
  • Plumbing and electrical pipeline installation (second and third floors): Advancing at an impressive 90%.
Building C:
  • Main structure: A work of architectural prowess, now standing at 100%.
  • First and second-floor masonry: Unfolding at 65%, respectively.
  • Plumbing and electrical pipeline installation (first floor): Laying the groundwork at 25%.
Building E:
  • Main structure: A complete embodiment of our vision at 100%.
  • First-floor masonry: Laying the foundation at 35%.
Building A1 & A2:
  • Main structures: A testament to our dedication at 100%.
  • First to fourth-floor masonry: Progressing 98%.
  • Plumbing and electrical pipeline installation: Moving forward at remarkable percentages.
Building A3:
  • Main structure: A masterpiece in the making, now standing at 100%.
  • Prefabricated piles (north side): A solid boundary completed at 100%.
Building A5: Encircling Progress
  • Perimeter wall beam pouring: Completing the enclosure at 80%.
  • East side of the river wall piles: Nearing completion at 65%.
  • Barrier installation: Creating boundaries at 50%.
Next Month’s Focus: Elevating Excellence
In the upcoming month, we are channeling our energy into:
  • Continuing the progress of ongoing projects.
  • Installing aluminum alloy doors and windows for Building A4.
  • Masonry construction for Buildings A5, E, D, A1, A2, A3, B, C.
  • Construction for A1, A2, A3, E, D wall plastering, river wall barrier, A5 north side road, water tank, and sewage treatment facilities.