Welcome to Sunshine Beach Resort & Resident’s September construction update. Explore the progress of our ambitious projects, where each brick and beam reflects our commitment to excellence. Here’s a glimpse of construction tapestry.
Building A4:
Plumbing and electrical pipelines on floors two to four: Completed at a stellar 100%.
Interior and exterior wall plastering: Meticulously finished at 100%.
Air conditioning installation: Progressing at 50%.
Model rooms: Taking shape at an impressive 30%.
Building A5:
Construction Progress:
Second-floor masonry: Laying the foundation at 30%.
Third-floor masonry: Soaring high at 95%.
Fourth-floor masonry: Solidifying at 90%.
Plumbing and electrical pipeline installation (floors two to four): Surging ahead at 90%.
Main structure: A towering achievement at 100%.
Floors one to four masonry: complete at 98%.
Plumbing and electrical pipeline installation (first and second floors): Nearly complete at 95%.
Building D:
Main structure: A monumental success at 100%.
Second to fifth-floor masonry: Progressing seamlessly at 95%.
Plumbing and electrical pipeline installation (second and third floors): Advancing at an impressive 90%.
Building C:
Main structure: A work of architectural prowess, now standing at 100%.
First and second-floor masonry: Unfolding at 65%, respectively.
Plumbing and electrical pipeline installation (first floor): Laying the groundwork at 25%.
Building E:
Main structure: A complete embodiment of our vision at 100%.
First-floor masonry: Laying the foundation at 35%.
Building A1 & A2:
Main structures: A testament to our dedication at 100%.
First to fourth-floor masonry: Progressing 98%.
Plumbing and electrical pipeline installation: Moving forward at remarkable percentages.
Building A3:
Main structure: A masterpiece in the making, now standing at 100%.
Prefabricated piles (north side): A solid boundary completed at 100%.
Building A5: Encircling Progress
Perimeter wall beam pouring: Completing the enclosure at 80%.
East side of the river wall piles: Nearing completion at 65%.
Barrier installation: Creating boundaries at 50%.
Next Month’s Focus: Elevating Excellence
In the upcoming month, we are channeling our energy into:
Continuing the progress of ongoing projects.
Installing aluminum alloy doors and windows for Building A4.
Masonry construction for Buildings A5, E, D, A1, A2, A3, B, C.
Construction for A1, A2, A3, E, D wall plastering, river wall barrier, A5 north side road, water tank, and sewage treatment facilities.