July: Construction Update 31.07.22 – Sunshine Beach Phuket

July: Construction Update 31.07.22

The construction update from July 31, 2022:

  • A4 Foundation construction is 100% complete, first floor construction is 20% complete;
  • A5 Pile construction is 100% complete, foundation construction is 100% complete;
  • Building E pile construction is 10% complete;
  • Building D foundation excavation is 100% complete and the pile construction starts;
  • Pool bar foundation construction is 100% complete.