Sunshine Beach Resort & Residences : Construction Update March 2024

Welcome to the latest update on the prestigious Sunshine Beach Resort & Residences, a flagship project by T.H. Group Phuket, poised to redefine luxury living in Phuket. As we delve into the intricate progress of this remarkable development, let’s explore the strides made in March 2024, bringing us closer to the realization of opulent condominiums and houses amidst breathtaking surroundings.

A Glimpse into Progress

In the heart of our endeavor lies meticulous attention to detail and relentless pursuit of excellence. Here’s a snapshot of the advancements across our various buildings:

A4 Building:

Floors 2-4: Aluminum alloy doors and windows, air conditioning installation, corridor and balcony puttying, room ceilings, and room tiles are 100% complete.

1st floor lobby renovation is 80% complete.

A5 Building:

Floors 1-4: Air conditioning installation, corridor and balcony puttying are 100% complete.

Room tiles are 30% complete, aluminum alloy doors and windows are 80% complete.

E Building:

Floors 1-5: Corridor and balcony puttying, 2 elevators are 100% complete. Aluminum alloy doors and windows are 88% complete, air-conditioning installation is 45% complete.

D Building:

Floors 1-5: Corridor and balcony puttying, 2 elevators, air conditioning installation are 100% complete.

C Building:

Floors 1-5: Corridor and balcony puttying, 2 elevators are 100% complete.

Aluminum alloy doors and windows are 85% complete.

B Building:

Floors 1-5: Corridor and balcony puttying are 100% complete.

Pipe wiring is 38% complete.

B Building:

Floors 1-5: Corridor and balcony puttying are 100% complete.

Pipe wiring is 38% complete.

A1 Building:

Floors 1-4: Air conditioning installation, corridor and balcony puttying, room ceilings, and room tiles are 100% complete.

Aluminum alloy doors and windows are 90% complete.

A2 Building:

Floors 1-4: Air conditioning installation, corridor and balcony puttying are 100% complete.

Room tiles are 48% complete, room ceilings are 25% complete, aluminum alloy doors and windows are 95% complete.

A3 Building:

Floors 1-4: Air conditioning installation, corridor and balcony puttying are 100% complete.

Room tiles are 27% complete, room ceilings are 30% complete, aluminum alloy doors and windows are 98% complete.

Perimeter Wall:

North side sections of rainwater pipes and roads for A5, D, and E buildings are 100% complete.

Swimming Pools:

Main structures of pools 3 and 7 are complete.

Milestones on the Horizon

As we look to the future, our focus sharpens on the following key endeavors:

Continued Construction Progress: The relentless pursuit of excellence drives us forward as we strive to uphold the highest standards across all ongoing projects. Aluminum Alloy Installation: Buildings B, D, and E are set to receive the hallmark of luxury with the installation of aluminum alloy doors and windows.

**Lobby Renovation Completion: **A4 building’s grand entrance nears completion, setting the stage for an unparalleled welcome experience. Interior Touches: From room ceilings to floor tiles, Buildings A2, A3, A5, B, C, D, and E are poised to receive meticulous interior finishes, elevating luxury to new heights.

Infrastructure Development: From sewage treatment facilities to road construction, every aspect of our development is meticulously crafted to ensure a seamless living experience. A Testament to Luxury

At Sunshine Beach Resort & Residences, luxury isn’t just a concept; it’s a way of life. With each milestone achieved, we inch closer to our vision of redefining luxury living in Phuket. Join us on this extraordinary journey as we pave the way for a lifestyle that’s as exclusive as it is exquisite.

Stay tuned for more updates as we continue to shape the epitome of luxury living at Sunshine Beach Resort & Residences.

For inquiries and sales, contact T.H. Group Phuket, the visionary minds behind this exceptional project.