Explore the latest developments at Sunshine Beach Resort & Residences, a beacon of sophistication in Phuket’s real estate landscape. Our November construction update unveils the meticulous progress across various buildings, marking significant milestones in the creation of a luxurious condotel and premium residences.

Building A4

Hydropower Pipeline Installation (2-4 Floors): Completed at 100%.

Windows Installation (2nd to 4th Floors): Currently at 40% completion.

Interior and Exterior Wall Plastering: Successfully completed at 100%.

Air Conditioning Sample Installations: In progress.

Glass Curtain Wall (1st-floor Hall): Successfully completed at 100%.

Stone Cave Molding Template Encapsulation: Accomplished at 100%.

Ceiling GRG Skeleton Welding: Currently underway.

Building A5

Second-floor Masonry: Reached 95% completion.

Masonry (3-4 Floors): Successfully completed at 100%.

Hydropower Pipeline Installation (2-4 Floors): Currently at 95% completion.

Building E

Main Structure: Successfully completed at 100%. Masonry (1-5 Floors):

Currently at 99% completion.

Embedded Hydropower Pipeline Installation (1-3 Floors):

Currently at 95% completion.

Hydropower Pipeline Installation (4th and 5th Floors):

Currently at 90% completion.

Interior Wall Plastering:

First and Second Floors: Currently at 90% completion.

Third Floors: Currently at 93% completion.

Four Floors: Currently at 30% completion.

Building D

Main Structure: Successfully completed at 100%.

Masonry (2nd Floor): Reached 98% completion.

Masonry (3-4 Floors): Successfully completed at 100%.

Masonry (5th Floors): Currently at 99% completion.

Embedded Hydropower Pipeline Installation (2-4 Floors):

Currently at 95% completion.

Interior Wall Plastering (2-4 Floors): Currently at 95% completion.

Interior Wall Plastering:

Four Floors of Slurry Rejection: Currently at 55% completion.

Third Floors: Currently at 80% completion.

Building C

Main Structure: Successfully completed at 100%.

Masonry (1-3 Floors): Currently at 99% completion.

Masonry (4-5 Floors): Currently at 95% completion.

Embedded Hydropower Pipeline Installation:

1st Floor: Currently at 95% completion.

2nd Floor: Currently at 90% completion.

3rd Floor: Currently at 75% completion.

Interior Wall Plastering: 1st Floor:

Currently at 95% completion.

2nd Floor: Currently at 75% completion.

Building B

Main Structure: Successfully completed at 100%.

Masonry: 1st Floor: Currently at 99% completion.

2nd and 3rd Floors: Currently at 97% completion.

4th and 5th Floors: Currently at 92% completion.

Embedded Hydropower Pipeline Installation:

1st Floor: Currently at 95% completion.

2nd Floor: Currently at 85% completion.

3rd Floor: Currently at 50% completion.

Building A1

Main Structure: Successfully completed at 100%.

Masonry: Successfully completed at 100%.

Embedded Hydropower Pipeline Installation:

1st and 2nd Floors: Currently at 100% completion.

3rd Floor: Currently at 95% completion.

Interior Wall Plastering:

1st to 4th Floors: Currently at 100% completion.

1st Floor: Currently at 100% completion.

2nd Floor: Currently at 25% completion.

Building A2

Main Structure: Successfully completed at 100%.

Masonry: Successfully completed at 100%.

Embedded Hydropower Pipeline Installation:

1st to 3rd Floors: Currently at 100% completion.

4th Floor: Currently at 80% completion.

Interior Wall Plastering:

1st to 4th Floors: Currently at 100% completion.

1st and 2nd Floors: Currently at 100% completion.

3rd Floor: Currently at 18% completion.

Building A3

Main Structure: Successfully completed at 100%.

Masonry: Successfully completed at 100%.

Embedded Hydropower Pipeline Installation (1-4 Floors):

Currently at 100% completion.

Interior Wall Plastering:

1st to 4th Floors: Currently at 100% completion.

1st Floor: Currently at 100% completion.

2nd Floor: Currently at 30% completion.

The Wall

Main Structure: Successfully completed at 100%.

Masonry: Successfully completed at 100%.

Embedded Hydropower Pipeline Installation (1-4 Floors):

Currently at 100% completion.

Interior Wall Plastering:

1st to 4th Floors: Currently at 100% completion.

1st Floor: Currently at 100% completion.

2nd Floor: Currently at 30% completion.